Case No.1
Upgrade of the FMM20-800-40-B101 filter press for Baiken-U LLP
Uranium mining · Kazakhstan · 2020
Task
Baiken-U LLP operated an FMM20-800-40-B101 filter press made by the Berdichev machine-building plant Progress (Ukraine). The equipment was technically obsolete, which limited throughput, required constant operator involvement and increased operating costs.
Solution
In 2020, Art Still Corporation LLP specialists carried out a comprehensive upgrade of the equipment:
- filter press overhaul
- complete replacement of the automation and instrumentation system
- upgrade of the electrical section
- restoration and repair of mechanical units
- replacement of worn components and consumables
- conversion of the equipment to a fully automatic cycle